Barajil and Bashtel Project
Starting Date : 03/10/2012
Client: Egyptian Natural Gas Holding Company “EGAS”
Scope of works for 250,000 customers:
• Land Survey, P&A Survey data and design.
• Contracts with customers.
• Construction of the medium pressure steel pipeline and polyethylene pipeline.
• Construction of the low pressure Polyethylene networks.
• Internal and External installation of 1”, ¾” & ½” steel pipes.
• Installation of Flues.
• Emergency , Operation and Maintenance for 20 Years.
• Bills collection for 20 years
No. Of Customer (Executed up to Date)
• Distribution 50,800 Cust.
• Internal &External Instillation 43,990 Cust.
• Conversion 43,243 Cust.
Network Information
• Polyethylene network 355mm: 32 mm) 130,950 L.M.
• External & Internal steel pipes 789,300 L.M.
Percentage of Completion : 87% Completed